The ore of the project is hematite. Based on this, Henan Shunzhi has compared and analyzed various beneficiation processes, and finally customized a beneficiation process that meets the actual conditions for the hematite beneficiation plant project.


Large-scale raw ore is continuously sent to jaw crusher through vibrating feeder for primary crushing, and then enters impact crusher for secondary crushing.

The crushed ore enters the circular vibrating screen for screening. For larger crushed ore, it will be sent back to the impact crusher again for continuous crushing.

Qualified materials are sent to the ball mill for grinding.

The minerals that have been ground by the ball mill are then screened by a magnetic separator to improve the grade of the minerals.